QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

ELGIN ENERGY ES CO LIMITED

Customer named in the TEC register

8projects in the register
1.7 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Longmorn Energy ParkLongmorn Energy Park 275kV SubstationStorage with solar or wind30015 Aug 2031Gate 1Scoping
Balrobert Farm BESSKnocknagael 132kV SubstationStorage15031 Oct 2032Gate 1Scoping
Denton Estate Solar PV and BESSNavenby 132kV SubstationStorage with solar or wind12930 Oct 2034 +12 moGate 1Scoping
West Grimsby FarmGrimsby West 132kV SubstationSolar15031 Oct 2035Gate 1Awaiting Consents
Saver & Pashley Farm Energy ParkNinfield GSPStorage with solar or wind1306 Dec 2036Not statedScoping
Vale of Neath (Rhigos Road)Hirwaun GSPStorage with solar or wind1206 Dec 2036Not statedScoping
Bellbroughton Energy ParkWarwickshire Connection Node A 400kV SubstationStorage with solar or wind50030 Oct 2037Gate 1Scoping
Lanehurst Farm BESSSussex and Romney Connection Node B 132kV SubstationStorage22531 Oct 2037Gate 1Scoping

Recent changes

  • Bellbroughton Energy ParkEngland and Wales, Storage with solar or windMarked as Gate 1
  • Denton Estate Solar PV and BESSEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2033 to 30 Oct 2034 (+12 months)+12 mo
  • Balrobert Farm BESSNorth Scotland, StorageMarked as Gate 1
  • Denton Estate Solar PV and BESSEngland and Wales, Storage with solar or windConnection point changed from Navenby 400kV Substation to Navenby 132kV Substation
  • Denton Estate Solar PV and BESSEngland and Wales, Storage with solar or windMarked as Gate 1
  • Lanehurst Farm BESSEngland and Wales, StorageConnection point changed from Bolney GSP to Sussex and Romney Connection Node B 132kV Substation
  • Lanehurst Farm BESSEngland and Wales, StorageMarked as Gate 1
  • Longmorn Energy ParkNorth Scotland, Storage with solar or windConnection point changed from Blackhillock 275kV Substation to Longmorn Energy Park 275kV Substation
  • West Grimsby FarmEngland and Wales, SolarMarked as Gate 1
  • West Grimsby FarmEngland and Wales, SolarConnection point changed from Grimsby West GSP to Grimsby West 132kV Substation
  • Longmorn Energy ParkNorth Scotland, Storage with solar or windMarked as Gate 1
  • Balrobert Farm BESSNorth Scotland, StorageCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • Bellbroughton Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • Denton Estate Solar PV and BESSEngland and Wales, Storage with solar or windCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • Lanehurst Farm BESSEngland and Wales, StorageCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • Longmorn Energy ParkNorth Scotland, Storage with solar or windCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • Saver & Pashley Farm Energy ParkEngland and Wales, Storage with solar or windCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • Vale of Neath (Rhigos Road)England and Wales, Storage with solar or windCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • West Grimsby FarmEngland and Wales, SolarCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
  • Balrobert Farm BESSNorth Scotland, StorageCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • Bellbroughton Energy ParkEngland and Wales, Storage with solar or windCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • Denton Estate Solar PV and BESSEngland and Wales, Storage with solar or windCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • Lanehurst Farm BESSEngland and Wales, StorageCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • Longmorn Energy ParkNorth Scotland, Storage with solar or windCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • Saver & Pashley Farm Energy ParkEngland and Wales, Storage with solar or windCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • Vale of Neath (Rhigos Road)England and Wales, Storage with solar or windCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • West Grimsby FarmEngland and Wales, SolarCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
  • Saver & Pashley Farm Energy ParkEngland and Wales, Storage with solar or windAdded to the registerNew
  • Vale of Neath (Rhigos Road)England and Wales, Storage with solar or windAdded to the registerNew
  • Lanehurst Farm BESSEngland and Wales, StorageAdded to the registerNew
  • Denton Estate Solar PV and BESSEngland and Wales, Storage with solar or windConnection point changed from Bicker Fen 400kV Substation to Navenby 400kV Substation
  • Bellbroughton Energy ParkEngland and Wales, Storage with solar or windConnection date moved from 30 Oct 2027 to 30 Oct 2037 (+120 months)+120 mo
  • Balrobert Farm BESSNorth Scotland, StorageAdded to the registerNew
  • Bellbroughton Energy ParkEngland and Wales, Storage with solar or windConnection point changed from Bellbroughton 275kV Energy Park to Warwickshire Connection Node A 400kV Substation
  • Bellbroughton Energy ParkEngland and Wales, Storage with solar or windAdded to the registerNew
  • Denton Estate Solar PV and BESSEngland and Wales, Storage with solar or windAdded to the registerNew
  • West Grimsby FarmEngland and Wales, SolarAdded to the registerNew
  • Longmorn Energy ParkNorth Scotland, Storage with solar or windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO