Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Walpole 400kV Substation

England and Wales, National Grid Electricity Transmission

5projects in the register
2.9 GWstill to connect
0 MWof that with Gate 2 offers
850 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Walpole 1 (Tertiary)WALPOLE GREEN LIMITEDStorage with solar or wind571 Aug 2025 Past dateNot statedScoping
Walpole Grid Services FacilityConrad (Walpole) LimitedOther013 Jul 2026 (0 MW)Not statedConsents Approved
Norfolk001EPL NEWCO1 LIMITEDStorage with solar or wind86030 Nov 2031Not statedScoping
Walpole Flexible GenerationFLEXIBLE GENERATION 1 LTDThermal (gas, biomass, waste)2,00030 Jun 2033Not statedScoping
Sutton BridgeSUTTON BRIDGE POWER GENERATIONThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

  • Walpole Grid Services FacilityEngland and Wales, OtherConnection date moved from 30 May 2025 to 13 Jul 2026 (+13 months)+13 mo
  • Walpole 1 (Tertiary)England and Wales, Storage with solar or windConnection date moved from 15 Jul 2025 to 1 Aug 2025 (+1 month)+1 mo
  • Norfolk001England and Wales, Storage with solar or windCustomer changed from EVOLUTION POWER LIMITED to EPL NEWCO1 LIMITED
  • Walpole 1 (Tertiary)England and Wales, Storage with solar or windStage removed (7.1 MW from 31 Oct 2023)
  • Walpole 1 (Tertiary)England and Wales, Storage with solar or windStage 1: Capacity changed from 49.9 MW to 57 MW
  • Walpole 1 (Tertiary)England and Wales, Storage with solar or windStage 1: Connection date moved from 1 May 2023 to 15 Jul 2025 (+26 months)+26 mo
  • Walpole Grid Services FacilityEngland and Wales, OtherConnection date moved from 31 May 2025 to 30 May 2025 (1 day earlier)
  • Walpole Grid Services FacilityEngland and Wales, OtherStatus changed from Awaiting Consents to Consents Approved
  • Walpole Flexible GenerationEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
  • Walpole Grid Services FacilityEngland and Wales, OtherAdded to the registerNew
  • Norfolk001England and Wales, Storage with solar or windAdded to the registerNew
  • Walpole 1 (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Walpole 400kV to Walpole 400kV Substation)
  • Walpole 1 (Tertiary)England and Wales, Storage with solar or windStage 1: Connection date moved from 5 Jan 2023 to 1 May 2023 (+4 months)+4 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO