Trent Valley North Connection Node B 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Tween Bridge Solar Park | RWE Renewables UK Solar and Storage Limited | Storage with solar or wind | 800 | 30 Oct 2029 | Not stated | Scoping |
| Kinoulton Solar & BESS | GREENTECH INVEST UK (16) LIMITED | Storage with solar or wind | 500 | 30 Oct 2034 | Gate 1 | Scoping |
| Epworth PV & BESS Station | IBV KELFIELD SOLAR LTD | Storage with solar or wind | 150 | 30 Oct 2035 −24 mo | Gate 1 | Scoping |
Recent changes
- Epworth PV & BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2037 to 30 Oct 2035 (−24 months)−24 mo
- Epworth PV & BESS StationEngland and Wales, Storage with solar or windConnection point changed from Keadby 400kV Substation to Trent Valley North Connection Node B 400kV Substation
- Epworth PV & BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Kinoulton Solar & BESSEngland and Wales, Storage with solar or windCustomer changed from GREENTECH PROJECTS HOLDING UK LIMITED to GREENTECH INVEST UK (16) LIMITED
- Kinoulton Solar & BESSEngland and Wales, Storage with solar or windConnection point changed from Stoke Bardolph 400kV Substation to Trent Valley North Connection Node B 400kV Substation
- Kinoulton Solar & BESSEngland and Wales, Storage with solar or windMarked as Gate 1
- Kinoulton Solar & BESSEngland and Wales, Storage with solar or windCustomer changed from Greentech Services Limited to GREENTECH PROJECTS HOLDING UK LIMITED
- Kinoulton Solar & BESSEngland and Wales, Storage with solar or windCustomer changed from GREENTECH PROJECTS HOLDING UK LIMITED to Greentech Services Limited
- Tween Bridge Solar ParkEngland and Wales, Storage with solar or windStage 1: Connection date moved from 31 Oct 2029 to 30 Oct 2029 (1 day earlier)
- Tween Bridge Solar ParkEngland and Wales, Storage with solar or windStage 3: Capacity changed from 0 MW to 210 MW
- Epworth PV & BESS StationEngland and Wales, Storage with solar or windCustomer changed from IB VOGT UK LTD to IBV KELFIELD SOLAR LTD
- Tween Bridge Solar ParkEngland and Wales, Storage with solar or windConnection point changed from Tween Bridge 400kV to Trent Valley North Connection Node B 400kV Substation
- Tween Bridge Solar ParkEngland and Wales, Storage with solar or windNew stage added (0 MW from 30 Oct 2037)
- Tween Bridge Solar ParkEngland and Wales, Storage with solar or windCustomer changed from RWE RENEWABLES UK ONSHORE WIND LIMITED to RWE RENEWABLES UK SOLAR AND STORAGE LIMITED
- Kinoulton Solar & BESSEngland and Wales, Storage with solar or windAdded to the registerNew
- Epworth PV & BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- Tween Bridge Solar ParkEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose