QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales
Connection date
30 Oct 2029
Gate
Not stated
Status
Scoping
Planning consent
Examination closed 12 Oct 2026
Tween Bridge Solar Farm (EN010148) · Source: Planning Inspectorate
Technology
Storage + Solar
Total capacity
800 MW
Connected now
0 MW
Still to connect
800 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001990
In the register since
May 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1034034030 Oct 2029Not statedScoping
2025059030 Nov 2032Not statedScoping
3021080030 Oct 2037Not statedScoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 30 Sep 2025 register
    Stage 1: Connection date moved from 31 Oct 2029 to 30 Oct 2029 (1 day earlier)
  • 30 Sep 2025 register
    Stage 3: Capacity changed from 0 MW to 210 MW
  • 29 Jul 2025 register
    Connection point changed from Tween Bridge 400kV to Trent Valley North Connection Node B 400kV Substation
  • 29 Jul 2025 register
    New stage added (0 MW from 30 Oct 2037)
  • 28 Feb 2025 register
    Customer changed from RWE RENEWABLES UK ONSHORE WIND LIMITED to RWE RENEWABLES UK SOLAR AND STORAGE LIMITED
  • 30 May 2023 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO