NatPower Teesside Green Energy Park
Old Rides Energy Storage Limited at Teeside Connection Node A 400kV Substation
- Connection date
- 31 Oct 2035
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004207
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Dec 2025 registerCustomer changed from NP SPV 27 Limited to Old Rides Energy Storage Limited
- 30 Sep 2025 registerStatus changed from Scoping to Consents Approved
- 29 Aug 2025 registerCustomer changed from NATPOWER MARINE LIMITED to NP SPV 27 Limited
- 24 Dec 2024 registerConnection point changed from Lackenby 400kV Substation to Teeside Connection Node A 400kV Substation
- 24 Dec 2024 registerCapacity changed from 1,034 MW to 1,000 MW
- 31 May 2024 registerCapacity changed from 1,000 MW to 1,034 MW
- 30 Jan 2024 registerAdded to the register
Also at Teeside Connection Node A 400kV Substation
Substation view1 other project, 1.2 GW still to connect at this substation in total. 240 MW is due to connect here before this project’s connection date of 31 Oct 2035.