Staffordshire Connection Node A 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Bradford Solar Farm | SolarFour Ltd | Solar | 960 | 30 Oct 2037 +48 mo | Gate 1 | Scoping |
| Bushbury | Bushbury 10 Renewables Limited | Solar | 1,000 | 30 Oct 2037 | Gate 1 | Scoping |
| Hill Street Solar PV/BESS Station | HILL STREET SHELFCO 1 LIMITED | Storage with solar or wind | 800 | 30 Oct 2037 | Gate 1 | Scoping |
Recent changes
- Hill Street Solar PV/BESS StationEngland and Wales, Storage with solar or windMarked as Gate 1
- Bradford Solar FarmEngland and Wales, SolarConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)+48 mo
- BushburyEngland and Wales, SolarMarked as Gate 1
- Bradford Solar FarmEngland and Wales, SolarMarked as Gate 1
- Bradford Solar FarmEngland and Wales, SolarConnection point changed from Ironbridge 400kV Substation to Staffordshire Connection Node A 400kV Substation
- BushburyEngland and Wales, SolarConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)+48 mo
- Hill Street Solar PV/BESS StationEngland and Wales, Storage with solar or windConnection point changed from Bushbury 275kV Substation to Staffordshire Connection Node A 400kV Substation
- Hill Street Solar PV/BESS StationEngland and Wales, Storage with solar or windConnection point changed from Bishops Wood GSP to Bushbury 275kV Substation
- Hill Street Solar PV/BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)+48 mo
- BushburyEngland and Wales, SolarConnection point changed from Bushbury 275kV Substation to Staffordshire Connection Node A 400kV Substation
- Hill Street Solar PV/BESS StationEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2031 to 31 Oct 2033 (+24 months)+24 mo
- BushburyEngland and Wales, SolarCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Bushbury 10 Renewables Limited
- Bradford Solar FarmEngland and Wales, SolarAdded to the registerNew
- Hill Street Solar PV/BESS StationEngland and Wales, Storage with solar or windAdded to the registerNew
- BushburyEngland and Wales, SolarAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?