Bradford Solar Farm
SolarFour Ltd at Staffordshire Connection Node A 400kV Substation
- Connection date
- 30 Oct 2037 +48 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Solar
- Total capacity
- 960 MW
- Connected now
- 0 MW
- Still to connect
- 960 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003511
- In the register since
- December 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)
- 17 Apr 2026 registerMarked as Gate 1
- 31 Jan 2025 registerConnection point changed from Ironbridge 400kV Substation to Staffordshire Connection Node A 400kV Substation
- 29 Dec 2023 registerAdded to the register
Also at Staffordshire Connection Node A 400kV Substation
Substation view2 other projects, 2.8 GW still to connect at this substation in total.