- Connection date
- 30 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Demand + Solar
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003409
- In the register since
- October 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 8 May 2026 registerMarked as Gate 1
- 24 Dec 2024 registerConnection date moved from 31 Oct 2033 to 30 Oct 2037 (+48 months)
- 27 Aug 2024 registerConnection point changed from Bushbury 275kV Substation to Staffordshire Connection Node A 400kV Substation
- 27 Feb 2024 registerCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Bushbury 10 Renewables Limited
- 31 Oct 2023 registerAdded to the register
Also at Staffordshire Connection Node A 400kV Substation
Substation view2 other projects, 2.8 GW still to connect at this substation in total.