Shin GSP
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|
Left the register since January 2021: Braelangwell Wind Farm (68 MW), Glencassley Wind Farm (65 MW).
Recent changes
- Braelangwell Wind FarmNorth Scotland, Onshore windLeft the register (68 MW from 1 Feb 2028)68 MW
- Glencassley Wind FarmNorth Scotland, Onshore windLeft the register (65 MW from 31 Oct 2026)65 MW
- Braelangwell Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Nov 2025 to 1 Feb 2028 (+26 months)+26 mo
- Braelangwell Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Shin 132/33kV GSP to Shin GSP)
- Glencassley Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Shin 132/33kV GSP to Shin GSP)
- Glencassley Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2025 to 31 Oct 2026 (+19 months)+19 mo
- Braelangwell Wind FarmNorth Scotland, Onshore windConnection date moved from 31 Dec 2023 to 30 Nov 2025 (+23 months)+23 mo
- Braelangwell Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Shin 132/33kV GSP Substation to Shin 132/33kV GSP)
- Glencassley Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Shin 132/33kV GSP Substation to Shin 132/33kV GSP)
- Braelangwell Wind FarmNorth Scotland, Onshore windCustomer changed from BROOKFIELD RENEWABLE UK LIMITED to WIND DEVELOPMENT HOLDINGS LIMITED
- Glencassley Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Apr 2024 to 1 Apr 2025 (+11 months)+11 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?