Transmission / Projects / North Scotland
Braelangwell Wind Farm
- Connection date
- Left 30 May 2025
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Onshore wind
- Total capacity
- 68 MW
- Connected now
- 0 MW
- Still to connect
- 68 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-000916
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 30 May 2025 registerLeft the register (68 MW from 1 Feb 2028)
- 31 Oct 2023 registerConnection date moved from 30 Nov 2025 to 1 Feb 2028 (+26 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Shin 132/33kV GSP to Shin GSP)
- 31 Dec 2021 registerConnection date moved from 31 Dec 2023 to 30 Nov 2025 (+23 months)
- 30 Nov 2021 registerSubstation name updated in the register (from Shin 132/33kV GSP Substation to Shin 132/33kV GSP)
- 29 Jun 2021 registerCustomer changed from BROOKFIELD RENEWABLE UK LIMITED to WIND DEVELOPMENT HOLDINGS LIMITED
Also at Shin GSP
Substation viewNo other projects in the register at this connection point.