Transmission / Projects / North Scotland

Glencassley Wind Farm

SSE RENEWABLES SERVICES (UK) LIMITED at Shin GSP

Connection date
Left 26 Apr 2024
Gate
Not stated
Status
Awaiting Consents
Technology
Onshore wind
Total capacity
65 MW
Connected now
0 MW
Still to connect
65 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Embedded
Region
North Scotland
Project number
PRO-000188
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 26 Apr 2024 register
    Left the register (65 MW from 31 Oct 2026)
  • 23 Dec 2022 register
    Substation name updated in the register (from Shin 132/33kV GSP to Shin GSP)
  • 29 Apr 2022 register
    Connection date moved from 1 Apr 2025 to 31 Oct 2026 (+19 months)
  • 30 Nov 2021 register
    Substation name updated in the register (from Shin 132/33kV GSP Substation to Shin 132/33kV GSP)
  • 30 Mar 2021 register
    Connection date moved from 30 Apr 2024 to 1 Apr 2025 (+11 months)

Also at Shin GSP

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO