Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Ratcliffe-On-Soar 400kV Substation

England and Wales, National Grid Electricity Transmission

2projects in the register
590 MWstill to connect
0 MWof that with Gate 2 offers
225 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Ratcliffe-on-Soar IIENSO GREEN HOLDINGS LIMITEDStorage with solar or wind59030 Oct 2033Gate 1Scoping
Ratcliffe on SoarUniper UK LimitedThermal (gas, biomass, waste)0ConnectedNot statedBuilt

Recent changes

  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Customer changed from C.GEN Killingholme Limited to Uniper UK Limited
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Customer changed from Uniper UK Limited to C.GEN Killingholme Limited
  • Ratcliffe-on-Soar IIEngland and Wales, Storage with solar or windMarked as Gate 1
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Storage to Storage, Gas (OCGT)
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Gas (OCGT) to Storage
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)1,796 MW no longer connected
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from −1,796 MW to 0 MW
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Connection date removed (was 1 Apr 2025)
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)796 MW now connectedConnected
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 1,225 MW to 225 MW
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 1 Apr 2025
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Demand, Gas (OCGT), Solar, Waste to Gas (OCGT)
  • Ratcliffe-on-Soar IIEngland and Wales, Storage with solar or windRestructured from 3 stages (200 MW from 31 Oct 2030, 100 MW from 31 Oct 2031, 100 MW from 31 Oct 2032) to 1 stage (590 MW from 30 Oct 2033). First connection date +36 months+36 mo
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)796 MW no longer connected
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Demand, Solar, Waste to Demand, Gas (OCGT), Solar, Waste
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Technology changed from Coal to Demand, Solar, Waste
  • Ratcliffe-on-Soar IIEngland and Wales, Storage with solar or windConnection point changed from Ratcliffe GSP to Ratcliffe-On-Soar 400kV Substation
  • Ratcliffe-on-Soar IIEngland and Wales, Storage with solar or windRenamed from Ratcliffe
  • Ratcliffe-on-Soar IIEngland and Wales, Storage with solar or windAdded to the registerNew
  • Ratcliffe on SoarEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Ratcliffe-On-Soar 400kV to Ratcliffe-On-Soar 400kV Substation)
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO