Ratcliffe-on-Soar II
ENSO GREEN HOLDINGS LIMITED at Ratcliffe-On-Soar 400kV Substation
- Connection date
- 30 Oct 2033
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 590 MW
- Connected now
- 0 MW
- Still to connect
- 590 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002158
- In the register since
- February 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 9 Dec 2025 registerMarked as Gate 1
- 24 Dec 2024 registerRestructured from 3 stages (200 MW from 31 Oct 2030, 100 MW from 31 Oct 2031, 100 MW from 31 Oct 2032) to 1 stage (590 MW from 30 Oct 2033). First connection date +36 months
- 28 Jul 2023 registerConnection point changed from Ratcliffe GSP to Ratcliffe-On-Soar 400kV Substation
- 31 Mar 2023 registerRenamed from Ratcliffe
- 28 Feb 2023 registerAdded to the register
Also at Ratcliffe-On-Soar 400kV Substation
Substation view1 other project, 590 MW still to connect at this substation in total.