Ratcliffe on Soar
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Storage + Gas (OCGT)
- Total capacity
- 225 MW
- Connected now
- 225 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000050
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jan 2026 registerCustomer changed from C.GEN Killingholme Limited to Uniper UK Limited
- 16 Dec 2025 registerCustomer changed from Uniper UK Limited to C.GEN Killingholme Limited
- 31 Oct 2025 registerTechnology changed from Storage to Storage, Gas (OCGT)
- 27 Jun 2025 registerTechnology changed from Gas (OCGT) to Storage
- 30 May 2025 register1,796 MW no longer connected
- 28 Mar 2025 registerCapacity changed from −1,796 MW to 0 MW
- 28 Mar 2025 registerConnection date removed (was 1 Apr 2025)
- 28 Feb 2025 register796 MW now connected
- 28 Feb 2025 registerCapacity changed from 1,225 MW to 225 MW
- 28 Feb 2025 registerConnection date set to 1 Apr 2025
- 28 Feb 2025 registerTechnology changed from Demand, Gas (OCGT), Solar, Waste to Gas (OCGT)
- 26 Nov 2024 register796 MW no longer connected
- 26 Nov 2024 registerTechnology changed from Demand, Solar, Waste to Demand, Gas (OCGT), Solar, Waste
- 27 Feb 2024 registerTechnology changed from Coal to Demand, Solar, Waste
- 23 Dec 2022 registerSubstation name updated in the register (from Ratcliffe-On-Soar 400kV to Ratcliffe-On-Soar 400kV Substation)
Also at Ratcliffe-On-Soar 400kV Substation
Substation view1 other project, 590 MW still to connect at this substation in total.