Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Ratcliffe-On-Soar 132kV Substation

England and Wales, National Grid Electricity Transmission

2projects in the register
190 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
EMERGE CentreUniper UK LimitedThermal (gas, biomass, waste)49.929 Jun 2029Gate 1Scoping
Ratcliffe Kegworth Road BEGAVOLTIS PEOPLE LIMITEDStorage with solar or wind14030 Oct 2033Not statedScoping

Left the register since January 2021: Ratcliffe-on-Soar (0 MW).

Recent changes

  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Status changed from Consents Approved to Scoping
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Marked as Gate 1
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windLeft the register (0 MW from 30 Jul 2029)0 MW
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windCapacity changed from 190 MW to 0 MW
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Customer changed from C.GEN Killingholme Limited to Uniper UK Limited
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Customer changed from Uniper UK Limited to C.GEN Killingholme Limited
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windMarked as Gate 1
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 1 Jul 2024 to 29 Jun 2029 (+60 months)+60 mo
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Status changed from Awaiting Consents to Consents Approved
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Renamed from Ratcliffe EMERGE
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Connection point changed from Ratcliffe GSP to Ratcliffe-On-Soar 132kV Substation
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2035 to 30 Jul 2029 (−75 months)−75 mo
  • Ratcliffe Kegworth Road BEGAEngland and Wales, Storage with solar or windCustomer changed from O&G Devco Limited to VOLTIS PEOPLE LIMITED
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (190 MW from 31 Oct 2035). First connection date +124 months+124 mo
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windConnection point changed from Ratcliffe-On-Soar 400kV Substation to Ratcliffe-On-Soar 132kV Substation
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage to Storage, Solar
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage to Storage, Solar
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windStage 3: Technology changed from Storage to Storage, Solar
  • Ratcliffe Kegworth Road BEGAEngland and Wales, Storage with solar or windAdded to the registerNew
  • Ratcliffe-on-SoarEngland and Wales, Storage with solar or windSubstation name updated in the register (from Ratcliffe-On-Soar 400kV to Ratcliffe-On-Soar 400kV Substation)
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Ratcliffe to Ratcliffe GSP)
  • EMERGE CentreEngland and Wales, Thermal (gas, biomass, waste)Added to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO