QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Transmission / Projects / England and Wales
Connection date
Left 7 Aug 2026
Gate
Gate 1
Status
Scoping
Technology
Storage + Solar
Total capacity
0 MW
Connected now
0 MW
Still to connect
0 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001361
In the register since
January 2021 or earlier

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 7 Aug 2026 register
    Left the register (0 MW from 30 Jul 2029)
  • 4 Aug 2026 register
    Capacity changed from 190 MW to 0 MW
  • 9 Dec 2025 register
    Marked as Gate 1
  • 27 Aug 2024 register
    Connection date moved from 31 Oct 2035 to 30 Jul 2029 (−75 months)
  • 31 May 2024 register
    Restructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (190 MW from 31 Oct 2035). First connection date +124 months
  • 27 Feb 2024 register
    Connection point changed from Ratcliffe-On-Soar 400kV Substation to Ratcliffe-On-Soar 132kV Substation
  • 27 Feb 2024 register
    Stage 1: Technology changed from Storage to Storage, Solar
  • 27 Feb 2024 register
    Stage 2: Technology changed from Storage to Storage, Solar
  • 27 Feb 2024 register
    Stage 3: Technology changed from Storage to Storage, Solar
  • 23 Dec 2022 register
    Substation name updated in the register (from Ratcliffe-On-Soar 400kV to Ratcliffe-On-Soar 400kV Substation)

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO