Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

EMERGE Centre

Uniper UK Limited at Ratcliffe-On-Soar 132kV Substation

Connection date
29 Jun 2029
Gate
Gate 1
Status
Scoping
Planning consent
Granted 24 Mar 2022
Rushcliffe, reference ES/4154 · Source: REPD
Technology
Waste
Total capacity
49.9 MW
Connected now
0 MW
Still to connect
49.9 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001462
In the register since
May 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 30 Oct 2026 register
    Status changed from Consents Approved to Scoping
  • 30 Oct 2026 register
    Marked as Gate 1
  • 27 Jan 2026 register
    Customer changed from C.GEN Killingholme Limited to Uniper UK Limited
  • 16 Dec 2025 register
    Customer changed from Uniper UK Limited to C.GEN Killingholme Limited
  • 27 Jun 2025 register
    Connection date moved from 1 Jul 2024 to 29 Jun 2029 (+60 months)
  • 27 Jun 2025 register
    Status changed from Awaiting Consents to Consents Approved
  • 30 May 2025 register
    Renamed from Ratcliffe EMERGE
  • 28 Feb 2025 register
    Connection point changed from Ratcliffe GSP to Ratcliffe-On-Soar 132kV Substation
  • 28 Oct 2022 register
    Substation name updated in the register (from Ratcliffe to Ratcliffe GSP)
  • 28 May 2021 register
    Added to the register

Also at Ratcliffe-On-Soar 132kV Substation

Substation view

1 other project, 190 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.