Peterhead 400kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Buchan 01 Offshore Wind Farm | BUCHAN OFFSHORE WIND LIMITED | Offshore wind | 960 | 31 Oct 2033 | Not stated | Scoping |
| Peterhead Battery | PETERHEAD FLEXPOWER LTD | Storage | 500 | 31 Oct 2033 | Gate 1 | Scoping |
| Stirling BESS | ANESCO LIMITED | Storage | 300 | 31 Oct 2033 | Gate 1 | Scoping |
| CENOS | FLOTATION ENERGY LIMITED | Offshore wind | 1,350 | 31 Oct 2035 | Not stated | Scoping |
Recent changes
- Peterhead BatteryNorth Scotland, StorageConnection point changed from Peterhead GSP to Peterhead 400kV Substation
- Peterhead BatteryNorth Scotland, StorageMarked as Gate 1
- Stirling BESSNorth Scotland, StorageMarked as Gate 1
- Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Buchan 01 275/66kV Substation to Peterhead 400kV Substation
- Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windCapacity changed from 932 MW to 960 MW
- CENOSNorth Scotland, Offshore windConnection point changed from Lackenby GSP to Peterhead 400kV Substation
- CENOSNorth Scotland, Offshore windCapacity changed from 1,500 MW to 1,350 MW
- CENOSNorth Scotland, Offshore windConnection date moved from 30 Oct 2033 to 31 Oct 2035 (+24 months)+24 mo
- CENOSNorth Scotland, Offshore windTransmission owner changed from NGET to SHET
- CENOSNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
- Stirling BESSNorth Scotland, StorageAdded to the registerNew
- Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windCustomer changed from BAYWA R.E. UK LIMITED to BUCHAN OFFSHORE WIND LIMITED
- Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Peterhead GSP to Buchan 01 275/66kV Substation
- Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Buchan 01 Offshore Wind Farm to Peterhead GSP
- CENOSNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY LIMITED to FLOTATION ENERGY PLC
- CENOSNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
- CENOSNorth Scotland, Offshore windSubstation name updated in the register (from Lackenby to Lackenby GSP)
- Peterhead BatteryNorth Scotland, StorageSubstation name updated in the register (from Peterhead to Peterhead GSP)
- CENOSNorth Scotland, Offshore windAdded to the registerNew
- Peterhead BatteryNorth Scotland, StorageCustomer changed from Scot Stability Limited to PETERHEAD FLEXPOWER LTD
- Peterhead BatteryNorth Scotland, StorageAdded to the registerNew
- Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose