Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Peterhead 400kV Substation

North Scotland, SSEN Transmission

4projects in the register
3.1 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Buchan 01 Offshore Wind FarmBUCHAN OFFSHORE WIND LIMITEDOffshore wind96031 Oct 2033Not statedScoping
Peterhead BatteryPETERHEAD FLEXPOWER LTDStorage50031 Oct 2033Gate 1Scoping
Stirling BESSANESCO LIMITEDStorage30031 Oct 2033Gate 1Scoping
CENOSFLOTATION ENERGY LIMITEDOffshore wind1,35031 Oct 2035Not statedScoping

Recent changes

  • Peterhead BatteryNorth Scotland, StorageConnection point changed from Peterhead GSP to Peterhead 400kV Substation
  • Peterhead BatteryNorth Scotland, StorageMarked as Gate 1
  • Stirling BESSNorth Scotland, StorageMarked as Gate 1
  • Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Buchan 01 275/66kV Substation to Peterhead 400kV Substation
  • Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windCapacity changed from 932 MW to 960 MW
  • CENOSNorth Scotland, Offshore windConnection point changed from Lackenby GSP to Peterhead 400kV Substation
  • CENOSNorth Scotland, Offshore windCapacity changed from 1,500 MW to 1,350 MW
  • CENOSNorth Scotland, Offshore windConnection date moved from 30 Oct 2033 to 31 Oct 2035 (+24 months)+24 mo
  • CENOSNorth Scotland, Offshore windTransmission owner changed from NGET to SHET
  • CENOSNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
  • Stirling BESSNorth Scotland, StorageAdded to the registerNew
  • Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windCustomer changed from BAYWA R.E. UK LIMITED to BUCHAN OFFSHORE WIND LIMITED
  • Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Peterhead GSP to Buchan 01 275/66kV Substation
  • Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windConnection point changed from Buchan 01 Offshore Wind Farm to Peterhead GSP
  • CENOSNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY LIMITED to FLOTATION ENERGY PLC
  • CENOSNorth Scotland, Offshore windCustomer changed from FLOTATION ENERGY PLC to FLOTATION ENERGY LIMITED
  • CENOSNorth Scotland, Offshore windSubstation name updated in the register (from Lackenby to Lackenby GSP)
  • Peterhead BatteryNorth Scotland, StorageSubstation name updated in the register (from Peterhead to Peterhead GSP)
  • CENOSNorth Scotland, Offshore windAdded to the registerNew
  • Peterhead BatteryNorth Scotland, StorageCustomer changed from Scot Stability Limited to PETERHEAD FLEXPOWER LTD
  • Peterhead BatteryNorth Scotland, StorageAdded to the registerNew
  • Buchan 01 Offshore Wind FarmNorth Scotland, Offshore windAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO