Buchan 01 Offshore Wind Farm
- Connection date
- 31 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Technology
- Offshore wind
- Total capacity
- 960 MW
- Connected now
- 0 MW
- Still to connect
- 960 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-001528
- In the register since
- July 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jan 2026 registerConnection point changed from Buchan 01 275/66kV Substation to Peterhead 400kV Substation
- 27 Jun 2025 registerCapacity changed from 932 MW to 960 MW
- 29 Sep 2023 registerCustomer changed from BAYWA R.E. UK LIMITED to BUCHAN OFFSHORE WIND LIMITED
- 29 Aug 2023 registerConnection point changed from Peterhead GSP to Buchan 01 275/66kV Substation
- 30 Jun 2023 registerConnection point changed from Buchan 01 Offshore Wind Farm to Peterhead GSP
- 30 Jul 2021 registerAdded to the register
Also at Peterhead 400kV Substation
Substation view3 other projects, 3.1 GW still to connect at this substation in total.