Pembroke (spare bay)
- Connection date
- 30 Jul 2028
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 120 MW
- Connected now
- 0 MW
- Still to connect
- 120 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000538
- In the register since
- July 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCustomer changed from ENSO GREEN HOLDINGS LIMITED to Pembroke Green Limited
- 27 Jun 2025 registerConnection date moved from 30 Oct 2026 to 30 Jul 2028 (+21 months)
- 27 Jun 2025 registerStatus changed from Scoping to Consents Approved
- 27 Jun 2025 registerTechnology changed from Storage, Solar to Storage
- 23 Dec 2022 registerSubstation name updated in the register (from Pembroke 132kV to Pembroke 132kV Substation)
- 30 Jul 2021 registerAdded to the register
Also at Pembroke 132kV Substation
Substation view1 other project, 215 MW still to connect at this substation in total. 95.3 MW is due to connect here before this project’s connection date of 30 Jul 2028.