Norton GSP
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Norton Solar Farm | RWE Renewables UK Solar and Storage Limited | Solar | 180 | 31 Oct 2031 | Not stated | Scoping |
| Hill House Farm Solar and Storage | BSR APPLICATIONS LIMITED | Storage with solar or wind | 99.9 | 30 Oct 2035 | Not stated | Scoping |
Left the register since January 2021: Norton GSP (312 MW).
Recent changes
- Norton Solar FarmEngland and Wales, SolarCustomer changed from JBM SOLAR PROJECTS 29 LIMITED to RWE RENEWABLES UK SOLAR AND STORAGE LIMITED
- Norton GSPEngland and Wales, Storage with solar or windLeft the register (312 MW from 30 Jul 2039)312 MW
- Hill House Farm Solar and StorageEngland and Wales, Storage with solar or windAdded to the registerNew
- Norton GSPEngland and Wales, Storage with solar or windAdded to the registerNew
- Norton Solar FarmEngland and Wales, SolarAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?