OVERTON440MW BESS
CARE POWER (OVERTON) LIMITED at North Humber Connection Node E 400kV Substation
- Connection date
- 30 Oct 2035
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 440 MW
- Connected now
- 0 MW
- Still to connect
- 440 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-003941
- In the register since
- June 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerCustomer changed from SMS ENERGY SERVICES LIMITED to CARE POWER (OVERTON) LIMITED
- 28 Mar 2025 registerConnection point changed from Overton IDNO GSP to North Humber Connection Node E 400kV Substation
- 28 Mar 2025 registerConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
- 28 Jun 2024 registerAdded to the register
Also at North Humber Connection Node E 400kV Substation
Substation view2 other projects, 1.7 GW still to connect at this substation in total. 1 GW is due to connect here before this project’s connection date of 30 Oct 2035.