Knocknagael 132kV Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Knocknagael BESS | FIELD KNOCKNAGAEL LTD | Storage | 200 | 30 Jul 2029 −15 mo | Gate 1 | Awaiting Consents |
| Balrobert Farm BESS | ELGIN ENERGY ES CO LIMITED | Storage | 150 | 31 Oct 2032 | Gate 1 | Scoping |
Left the register since January 2021: Leys Energy Storage (400 MW).
Recent changes
- Knocknagael BESSNorth Scotland, StorageConnection date moved from 30 Jun 2029 to 30 Jul 2029 (+1 month)+1 mo
- Knocknagael BESSNorth Scotland, StorageConnection date moved from 31 Oct 2030 to 30 Jun 2029 (−16 months)−16 mo
- Balrobert Farm BESSNorth Scotland, StorageMarked as Gate 1
- Knocknagael BESSNorth Scotland, StorageMarked as Gate 1
- Balrobert Farm BESSNorth Scotland, StorageCustomer changed from Elgin Energy Holdings Limited to ELGIN ENERGY ES CO LIMITED
- Balrobert Farm BESSNorth Scotland, StorageCustomer changed from ELGIN ENERGY ES CO LIMITED to Elgin Energy Holdings Limited
- Knocknagael BESSNorth Scotland, StorageCustomer changed from Virmati Energy Ltd to FIELD KNOCKNAGAEL LIMITED
- Leys Energy StorageNorth Scotland, StorageLeft the register (400 MW from 31 Oct 2032)400 MW
- Balrobert Farm BESSNorth Scotland, StorageAdded to the registerNew
- Knocknagael BESSNorth Scotland, StorageCustomer changed from Field Gaia Ltd to VIRMATI ENERGY LTD
- Knocknagael BESSNorth Scotland, StorageStatus changed from Scoping to Awaiting Consents
- Knocknagael BESSNorth Scotland, StorageCustomer changed from VIRMATI ENERGY LTD to Field Gaia Ltd
- Leys Energy StorageNorth Scotland, StorageAdded to the registerNew
- Knocknagael BESSNorth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?