Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Knocknagael BESS

FIELD KNOCKNAGAEL LTD at Knocknagael 132kV Substation

Connection date
30 Jul 2029 −15 months since 9 Dec
Gate
Gate 1
Status
Awaiting Consents
Planning consent
Granted 4 Feb 2026
Scottish Government (S36), reference ECU00005099 · Source: REPD
Technology
Storage
Total capacity
200 MW
Connected now
0 MW
Still to connect
200 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-003712
In the register since
May 2023

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 16 Oct 2026 register
    Connection date moved from 30 Jun 2029 to 30 Jul 2029 (+1 month)
  • 10 Oct 2026 register
    Connection date moved from 31 Oct 2030 to 30 Jun 2029 (−16 months)
  • 14 Apr 2026 register
    Marked as Gate 1
  • 28 Feb 2025 register
    Customer changed from Virmati Energy Ltd to FIELD KNOCKNAGAEL LIMITED
  • 29 Oct 2024 register
    Customer changed from Field Gaia Ltd to VIRMATI ENERGY LTD
  • 29 Oct 2024 register
    Status changed from Scoping to Awaiting Consents
  • 31 May 2024 register
    Customer changed from VIRMATI ENERGY LTD to Field Gaia Ltd
  • 30 May 2023 register
    Added to the register

Also at Knocknagael 132kV Substation

Substation view

1 other project, 350 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.