Knocknagael BESS
- Connection date
- 30 Jul 2029 −15 months since 9 Dec
- Gate
- Gate 1
- Status
- Awaiting Consents
- Planning consent
- Granted 4 Feb 2026
Scottish Government (S36), reference ECU00005099 · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-003712
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerConnection date moved from 30 Jun 2029 to 30 Jul 2029 (+1 month)
- 10 Oct 2026 registerConnection date moved from 31 Oct 2030 to 30 Jun 2029 (−16 months)
- 14 Apr 2026 registerMarked as Gate 1
- 28 Feb 2025 registerCustomer changed from Virmati Energy Ltd to FIELD KNOCKNAGAEL LIMITED
- 29 Oct 2024 registerCustomer changed from Field Gaia Ltd to VIRMATI ENERGY LTD
- 29 Oct 2024 registerStatus changed from Scoping to Awaiting Consents
- 31 May 2024 registerCustomer changed from VIRMATI ENERGY LTD to Field Gaia Ltd
- 30 May 2023 registerAdded to the register
Also at Knocknagael 132kV Substation
Substation view1 other project, 350 MW still to connect at this substation in total.