Keith 2 132/33kV GSP Substation
North Scotland, SSEN Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Drum Farm Energy Storage Facility | Field Drum Farm Ltd | Storage | 49.9 | 31 Oct 2026 Past date −24 mo | Gate 2 | Consents Approved |
| Garbet Wind Farm | GARBET WIND FARM LLP | Onshore wind | 46.2 | 31 Oct 2026 Past date | Gate 2 | Consents Approved |
| Hill of Towie 2 Wind Farm | GREENHILLS 1 LIMITED | Onshore wind | 36 | 1 Jun 2030 | Gate 2 | Consents Approved |
Recent changes
- Hill of Towie 2 Wind FarmNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Drum Farm Energy Storage FacilityNorth Scotland, StorageConnection date moved from 31 Oct 2028 to 31 Oct 2026 (−24 months)−24 mo
- Drum Farm Energy Storage FacilityNorth Scotland, StorageStatus changed from Scoping to Consents Approved
- Drum Farm Energy Storage FacilityNorth Scotland, StorageSubstation name updated in the register (from Keith 2 GSP to Keith 2 132/33kV GSP Substation)
- Drum Farm Energy Storage FacilityNorth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Garbet Wind FarmNorth Scotland, Onshore windRestructured from 1 stage (46.2 MW from 31 Oct 2026) to 1 stage (46.2 MW from 31 Oct 2026)
- Garbet Wind FarmNorth Scotland, Onshore windConnection point changed from Keith GSP to Keith 2 132/33kV GSP Substation
- Hill of Towie 2 Wind FarmNorth Scotland, Onshore windConnection point changed from Keith GSP to Keith 2 132/33kV GSP Substation
- Drum Farm Energy Storage FacilityNorth Scotland, StorageConnection point changed from Keith 1 132/33kV GSP Substation to Keith 2 GSP
- Garbet Wind FarmNorth Scotland, Onshore windCustomer changed from ENERGYFARM UK GARBET LLP to GARBET WIND FARM LLP
- Hill of Towie 2 Wind FarmNorth Scotland, Onshore windCustomer changed from Cairn Duhie Energy Limited to GREENHILLS 1 LIMITED
- Hill of Towie 2 Wind FarmNorth Scotland, Onshore windCustomer changed from Renewable Energy Systems Limited to Cairn Duhie Energy Limited
- Drum Farm Energy Storage FacilityNorth Scotland, StorageConnection point changed from Keith GSP to Keith 1 132/33kV GSP Substation
- Drum Farm Energy Storage FacilityNorth Scotland, StorageCustomer changed from Drum Farm Energy Storage Limited Novation to Field Drum Farm Ltd
- Drum Farm Energy Storage FacilityNorth Scotland, StorageCustomer changed from Renewable Energy Systems Limited to Drum Farm Energy Storage Limited Novation
- Hill of Towie 2 Wind FarmNorth Scotland, Onshore windConnection date moved from 27 Jun 2025 to 1 Jun 2030 (+59 months)+59 mo
- Garbet Wind FarmNorth Scotland, Onshore windAdded to the registerNew
- Drum Farm Energy Storage FacilityNorth Scotland, StorageAdded to the registerNew
- Hill of Towie 2 Wind FarmNorth Scotland, Onshore windConnection point changed from Keith 2 to Keith GSP
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?