Garbet Wind Farm
- Connection date
- 31 Oct 2026
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted on appeal 26 Sep 2022
Moray, reference 21/00020/EIA · Source: REPD - Contract for Difference
- Allocation Round 5
- Technology
- Onshore wind
- Total capacity
- 46.2 MW
- Connected now
- 0 MW
- Still to connect
- 46.2 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001813
- In the register since
- August 2023
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Jul 2026 registerRestructured from 1 stage (46.2 MW from 31 Oct 2026) to 1 stage (46.2 MW from 31 Oct 2026)
- 6 Feb 2026 registerConnection point changed from Keith GSP to Keith 2 132/33kV GSP Substation
- 29 Aug 2025 registerCustomer changed from ENERGYFARM UK GARBET LLP to GARBET WIND FARM LLP
- 29 Aug 2023 registerAdded to the register
Also at Keith 2 132/33kV GSP Substation
Substation view2 other projects, 132 MW still to connect at this substation in total.