Drum Farm Energy Storage Facility
- Connection date
- 31 Oct 2026 −24 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 27 Oct 2022
Moray, reference 22/00715/APP · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001726
- In the register since
- August 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Sep 2026 registerConnection date moved from 31 Oct 2028 to 31 Oct 2026 (−24 months)
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 1 Sep 2026 registerSubstation name updated in the register (from Keith 2 GSP to Keith 2 132/33kV GSP Substation)
- 1 Sep 2026 registerGiven a Gate 2 connection offer
- 29 Aug 2025 registerConnection point changed from Keith 1 132/33kV GSP Substation to Keith 2 GSP
- 28 Mar 2025 registerConnection point changed from Keith GSP to Keith 1 132/33kV GSP Substation
- 26 Nov 2024 registerCustomer changed from Drum Farm Energy Storage Limited Novation to Field Drum Farm Ltd
- 29 Oct 2024 registerCustomer changed from Renewable Energy Systems Limited to Drum Farm Energy Storage Limited Novation
- 30 Aug 2022 registerAdded to the register
Also at Keith 2 132/33kV GSP Substation
Substation view2 other projects, 132 MW still to connect at this substation in total.