IPC Grid Tremorfa
IPC GRID CONNECTION LIMITED at Imperial Park B 400kV Substation
- Connection date
- 6 Dec 2036
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003765
- In the register since
- November 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Jun 2026 registerMarked as Gate 1
- 29 Oct 2024 registerConnection point changed from Imperial Park 400kV Substation to Imperial Park B 400kV Substation
- 27 Sep 2024 registerCapacity changed from 500 MW to 1,000 MW
- 27 Sep 2024 registerConnection date moved from 31 Oct 2037 to 6 Dec 2036 (−11 months)
- 26 Mar 2024 registerConnection point changed from Tremorfa 275kV Substation to Imperial Park 400kV Substation
- 28 Nov 2023 registerAdded to the register
Also at Imperial Park B 400kV Substation
Substation view1 other project, 1.4 GW still to connect at this substation in total.