Hartmoor 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Worset PV & BESS Park | Worcestershire Solar 1 Limited | Storage with solar or wind | 37.5 | 30 Oct 2027 +41 mo | Gate 2 | Under Construction/Commissioning |
| WORSET LANE BESS | FIELD HARTMOOR LTD | Storage | 200 | 31 May 2029 +31 mo | Gate 2 | Consents Approved |
Left the register since January 2021: Worset Solar Park (38 MW), Tamar-Hartmoor (0 MW).
Recent changes
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windStatus changed from Consents Approved to Under Construction/Commissioning
- WORSET LANE BESSEngland and Wales, StorageConnection date moved from 25 Oct 2026 to 31 May 2029 (+31 months)+31 mo
- WORSET LANE BESSEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windConnection date moved from 7 Jun 2024 to 30 Oct 2027 (+41 months)+41 mo
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- Tamar-HartmoorEngland and Wales, OtherLeft the register (0 MW from 30 Oct 2026)0 MW
- WORSET LANE BESSEngland and Wales, StorageCustomer changed from HARTFINDER ONE LIMITED to FIELD HARTMOOR LTD
- Tamar-HartmoorEngland and Wales, OtherConnection date moved from 31 May 2025 to 30 Oct 2026 (+17 months)+17 mo
- WORSET LANE BESSEngland and Wales, StorageConnection date moved from 28 Oct 2033 to 25 Oct 2026 (−84 months)−84 mo
- WORSET LANE BESSEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windConnection point changed from Hartmoor GSP to Hartmoor 275kV Substation
- Tamar-HartmoorEngland and Wales, OtherAdded to the registerNew
- WORSET LANE BESSEngland and Wales, StorageAdded to the registerNew
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windCustomer changed from CS UK HOLDINGS III LIMITED to Worcestershire Solar 1 Limited
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windCustomer changed from Worcestershire Solar 1 Limited to CS UK HOLDINGS III LIMITED
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windSubstation name updated in the register (from Hartmoor to Hartmoor GSP)
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windCustomer changed from CS UK HOLDINGS III LIMITED to Worcestershire Solar 1 Limited
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2022 to 7 Jun 2024 (+19 months)+19 mo
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
- Worset PV & BESS ParkEngland and Wales, Storage with solar or windAdded to the registerNew
- Worset Solar ParkEngland and Wales, SolarLeft the register (38 MW from 30 Sep 2021)38 MW
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?