Transmission / Projects / England and Wales

Tamar-Hartmoor

TI PROJECTCO 3 LIMITED at Hartmoor 275kV Substation

Connection date
Left 24 Dec 2024
Gate
Not stated
Status
Scoping
Technology
Reactive compensation
Total capacity
0 MW
Connected now
0 MW
Still to connect
0 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002570
In the register since
June 2023

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 24 Dec 2024 register
    Left the register (0 MW from 30 Oct 2026)
  • 26 Nov 2024 register
    Connection date moved from 31 May 2025 to 30 Oct 2026 (+17 months)
  • 30 Jun 2023 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO