WORSET LANE BESS
- Connection date
- 31 May 2029 +31 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 18 Jan 2023
Hartlepool, reference H/2022/0263 · Source: REPD - Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003650
- In the register since
- May 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Jul 2026 registerConnection date moved from 25 Oct 2026 to 31 May 2029 (+31 months)
- 24 Jul 2026 registerGiven a Gate 2 connection offer
- 26 Nov 2024 registerCustomer changed from HARTFINDER ONE LIMITED to FIELD HARTMOOR LTD
- 31 May 2024 registerConnection date moved from 28 Oct 2033 to 25 Oct 2026 (−84 months)
- 28 Jul 2023 registerStatus changed from Scoping to Consents Approved
- 30 May 2023 registerAdded to the register
Also at Hartmoor 275kV Substation
Substation view1 other project, 238 MW still to connect at this substation in total. 37.5 MW is due to connect here before this project’s connection date of 31 May 2029.