Gwyddelwern 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Gaerwen Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind | 67 | 1 Jun 2027 | Not stated | Awaiting Consents |
| Mwdwl Eithin Energy Park | MOEL CHWA ENERGY PARK LIMITED | Onshore wind | 81.2 | 30 Jun 2030 | Not stated | Scoping |
| Derwydd Bach Energy Park | CONSTANTINE WIND ENERGY LIMITED | Onshore wind | 85 | 31 Oct 2037 | Gate 1 | Scoping |
Left the register since January 2021: Gwyddelwern BESS (500 MW).
Recent changes
- Derwydd Bach Energy ParkEngland and Wales, Onshore windMarked as Gate 1
- Mwdwl Eithin Energy ParkEngland and Wales, Onshore windStage removed (0 MW from 30 Oct 2032)
- Mwdwl Eithin Energy ParkEngland and Wales, Onshore windRestructured from 1 stage (81.2 MW from 31 Oct 2026) to 2 stages (81.2 MW from 30 Jun 2030, 0 MW from 30 Oct 2032). First connection date +44 months+44 mo
- Derwydd Bach Energy ParkEngland and Wales, Onshore windAdded to the registerNew
- Gwyddelwern BESSEngland and Wales, StorageLeft the register (500 MW from 31 Oct 2037)500 MW
- Mwdwl Eithin Energy ParkEngland and Wales, Onshore windCustomer changed from MWDWL EITHIN ENERGY PARK LIMITED to MOEL CHWA ENERGY PARK LIMITED
- Gwyddelwern BESSEngland and Wales, StorageAdded to the registerNew
- Mwdwl Eithin Energy ParkEngland and Wales, Onshore windConnection point changed from Bodelwyddan 400kV Substation to Gwyddelwern 400kV Substation
- Mwdwl Eithin Energy ParkEngland and Wales, Onshore windSubstation name updated in the register (from Bodelwyddan 400kV to Bodelwyddan 400kV Substation)
- Gaerwen Wind FarmEngland and Wales, Onshore windAdded to the registerNew
- Mwdwl Eithin Energy ParkEngland and Wales, Onshore windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?