Mwdwl Eithin Energy Park
MOEL CHWA ENERGY PARK LIMITED at Gwyddelwern 400kV Substation
- Connection date
- 30 Jun 2030
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 81.2 MW
- Connected now
- 0 MW
- Still to connect
- 81.2 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001511
- In the register since
- June 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Sep 2025 registerStage removed (0 MW from 30 Oct 2032)
- 29 Jul 2025 registerRestructured from 1 stage (81.2 MW from 31 Oct 2026) to 2 stages (81.2 MW from 30 Jun 2030, 0 MW from 30 Oct 2032). First connection date +44 months
- 27 Feb 2024 registerCustomer changed from MWDWL EITHIN ENERGY PARK LIMITED to MOEL CHWA ENERGY PARK LIMITED
- 29 Sep 2023 registerConnection point changed from Bodelwyddan 400kV Substation to Gwyddelwern 400kV Substation
- 30 Mar 2022 registerSubstation name updated in the register (from Bodelwyddan 400kV to Bodelwyddan 400kV Substation)
- 29 Jun 2021 registerAdded to the register
Also at Gwyddelwern 400kV Substation
Substation view2 other projects, 233 MW still to connect at this substation in total. 67 MW is due to connect here before this project’s connection date of 30 Jun 2030.