QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Ferrybridge B 132kV Substation

England and Wales, National Grid Electricity Transmission

3projects in the register
300 MWstill to connect
0 MWof that with Gate 2 offers
150 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Ferrybridge B BESS & Solar SubstationO&G Solar (SPV 19) LimitedStorage with solar or wind99.924 Oct 2035Not statedConsents Approved
NEL TigerUE 1 LTDStorage20030 Oct 2035Not statedScoping
SSE Ferrybridge BESSSSE BATTERY SALISBURY LIMITEDStorage0ConnectedNot statedBuilt

Recent changes

  • SSE Ferrybridge BESSEngland and Wales, StorageCustomer changed from SSE FERRYBRIDGE BATTERY LIMITED to SSE BATTERY SALISBURY LIMITED
  • NEL TigerEngland and Wales, StorageCustomer changed from Newton Energi Limited to UE 1 LTD
  • SSE Ferrybridge BESSEngland and Wales, StorageRestructured from 3 stages (150 MW connected, 0 MW from 2 Apr 2027, 0 MW from 30 Oct 2035) to 1 stage (150 MW connected)
  • SSE Ferrybridge BESSEngland and Wales, StorageRestructured from 1 stage (150 MW from 2 May 2025) to 3 stages (150 MW connected, 0 MW from 2 Apr 2027, 0 MW from 30 Oct 2035)
  • SSE Ferrybridge BESSEngland and Wales, StorageConnection date moved from 28 Jun 2024 to 2 May 2025 (+10 months)+10 mo
  • SSE Ferrybridge BESSEngland and Wales, StorageTechnology changed from Storage to Demand, Storage
  • SSE Ferrybridge BESSEngland and Wales, StorageCustomer changed from SSE FERRYBRIDGE BATTERY LIMITED to SSE UTILITY SOLUTIONS LIMITED
  • SSE Ferrybridge BESSEngland and Wales, StorageCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE FERRYBRIDGE BATTERY LIMITED
  • Ferrybridge B BESS & Solar SubstationEngland and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
  • NEL TigerEngland and Wales, StorageConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
  • NEL TigerEngland and Wales, StorageAdded to the registerNew
  • Ferrybridge B BESS & Solar SubstationEngland and Wales, Storage with solar or windRenamed from Ferrybridge BESS & Solar Substation
  • Ferrybridge B BESS & Solar SubstationEngland and Wales, Storage with solar or windAdded to the registerNew
  • SSE Ferrybridge BESSEngland and Wales, StorageStatus changed from Scoping to Consents Approved
  • SSE Ferrybridge BESSEngland and Wales, StorageAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO