SSE Ferrybridge BESS
SSE BATTERY SALISBURY LIMITED at Ferrybridge B 132kV Substation
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Demand + Storage
- Total capacity
- 150 MW
- Connected now
- 150 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001614
- In the register since
- March 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 13 Oct 2026 registerCustomer changed from SSE FERRYBRIDGE BATTERY LIMITED to SSE BATTERY SALISBURY LIMITED
- 30 Sep 2025 registerRestructured from 3 stages (150 MW connected, 0 MW from 2 Apr 2027, 0 MW from 30 Oct 2035) to 1 stage (150 MW connected)
- 29 Jul 2025 registerRestructured from 1 stage (150 MW from 2 May 2025) to 3 stages (150 MW connected, 0 MW from 2 Apr 2027, 0 MW from 30 Oct 2035)
- 27 Jun 2025 registerConnection date moved from 28 Jun 2024 to 2 May 2025 (+10 months)
- 27 Jun 2025 registerTechnology changed from Storage to Demand, Storage
- 24 Dec 2024 registerCustomer changed from SSE FERRYBRIDGE BATTERY LIMITED to SSE UTILITY SOLUTIONS LIMITED
- 26 Nov 2024 registerCustomer changed from SSE UTILITY SOLUTIONS LIMITED to SSE FERRYBRIDGE BATTERY LIMITED
- 28 Feb 2023 registerStatus changed from Scoping to Consents Approved
- 30 Mar 2022 registerAdded to the register
Also at Ferrybridge B 132kV Substation
Substation view2 other projects, 300 MW still to connect at this substation in total.