NEL Tiger
- Connection date
- 30 Oct 2035
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Embedded
- Region
- England and Wales
- Project number
- PRO-002815
- In the register since
- January 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Apr 2026 registerCustomer changed from Newton Energi Limited to UE 1 LTD
- 27 Sep 2024 registerConnection date moved from 31 Oct 2035 to 30 Oct 2035 (1 day earlier)
- 30 Jan 2024 registerAdded to the register
Also at Ferrybridge B 132kV Substation
Substation view2 other projects, 300 MW still to connect at this substation in total. 99.9 MW is due to connect here before this project’s connection date of 30 Oct 2035.