Eccles 400/132kV
South Scotland, SP Energy Networks
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| AMP Eccles BESS | Eccles Grid Stability Limited | Storage | 49.9 | 31 Oct 2029 | Not stated | Scoping |
| Coldstream BESS | IGP ENERGY STORAGE 4 LIMITED | Storage | 50 | 31 Oct 2030 | Gate 1 | Scoping |
| Pittlesheugh Farm | Pittlesheugh Farm BESS Limited | Storage | 340 | 31 Oct 2030 | Gate 1 | Scoping |
Recent changes
- Pittlesheugh FarmSouth Scotland, StorageConnection date moved from 30 Oct 2030 to 31 Oct 2030 (1 day later)
- Pittlesheugh FarmSouth Scotland, StorageConnection date moved from 31 Oct 2030 to 30 Oct 2030 (1 day earlier)
- Pittlesheugh FarmSouth Scotland, StorageMarked as Gate 1
- Coldstream BESSSouth Scotland, StorageMarked as Gate 1
- Pittlesheugh FarmSouth Scotland, StorageCustomer changed from C A Ramsay Partnership to Pittlesheugh Farm BESS Limited
- AMP Eccles BESSSouth Scotland, StorageConnection point changed from Eccles 132kV Substation to Eccles 400/132kV
- Coldstream BESSSouth Scotland, StorageConnection point changed from Eccles 132kV Substation to Eccles 400/132kV
- Pittlesheugh FarmSouth Scotland, StorageConnection point changed from Eccles 132kV Substation to Eccles 400/132kV
- Coldstream BESSSouth Scotland, StorageAdded to the registerNew
- AMP Eccles BESSSouth Scotland, StorageAdded to the registerNew
- Pittlesheugh FarmSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?