Coldstream BESS
- Connection date
- 31 Oct 2030
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003572
- In the register since
- July 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 28 Nov 2025 registerMarked as Gate 1
- 29 Oct 2024 registerConnection point changed from Eccles 132kV Substation to Eccles 400/132kV
- 30 Jul 2024 registerAdded to the register
Also at Eccles 400/132kV
Substation view2 other projects, 440 MW still to connect at this substation in total. 49.9 MW is due to connect here before this project’s connection date of 31 Oct 2030.