AMP Eccles BESS
- Connection date
- 31 Oct 2029
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted 15 Jun 2023
Scottish Borders, reference 22/01988/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-003836
- In the register since
- December 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Oct 2024 registerConnection point changed from Eccles 132kV Substation to Eccles 400/132kV
- 29 Dec 2023 registerAdded to the register
Also at Eccles 400/132kV
Substation view2 other projects, 440 MW still to connect at this substation in total.