Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Drax 132kV Substation

England and Wales, National Grid Electricity Transmission

2projects in the register
190 MWstill to connect
0 MWof that with Gate 2 offers
99.9 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
DraxENSO GREEN HOLDINGS D LIMITEDStorage with solar or wind19030 Oct 2029Not statedAwaiting Consents
Lakeside Energy DraxLAKESIDE ENERGY STORAGE LIMITEDStorage0ConnectedNot statedBuilt

Recent changes

  • DraxEngland and Wales, Storage with solar or windStatus changed from Scoping to Awaiting Consents
  • Lakeside Energy DraxEngland and Wales, Storage0.9 MW now connectedConnected
  • Lakeside Energy DraxEngland and Wales, StorageCapacity changed from 99 MW to 99.9 MW
  • Lakeside Energy DraxEngland and Wales, Storage99 MW now connectedConnected
  • Lakeside Energy DraxEngland and Wales, StorageCapacity changed from 99.9 MW to 99 MW
  • Lakeside Energy DraxEngland and Wales, StorageConnection date moved from 29 Mar 2024 to 29 Sep 2024 (+6 months)+6 mo
  • Lakeside Energy DraxEngland and Wales, StorageStatus changed from Consents Approved to Built
  • DraxEngland and Wales, Storage with solar or windConnection point changed from Drax 400kV Substation to Drax 132kV Substation
  • DraxEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2025 to 30 Oct 2029 (+52 months)+52 mo
  • DraxEngland and Wales, Storage with solar or windTechnology changed from Storage to Storage, Solar
  • Lakeside Energy DraxEngland and Wales, StorageSubstation name updated in the register (from Drax GSP to Drax 132kV Substation)
  • DraxEngland and Wales, Storage with solar or windRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (190 MW from 30 Jun 2025)
  • Lakeside Energy DraxEngland and Wales, StorageConnection date moved from 31 Oct 2023 to 29 Mar 2024 (+5 months)+5 mo
  • DraxEngland and Wales, Storage with solar or windConnection point changed from Drax to Drax 400kV Substation
  • Lakeside Energy DraxEngland and Wales, StorageConnection point changed from Drax to Drax GSP
  • Lakeside Energy DraxEngland and Wales, StorageCustomer changed from RENEWABLE ENERGY SYSTEMS LIMITED to Lakeside Energy Storage Limited
  • Lakeside Energy DraxEngland and Wales, StorageAdded to the registerNew
  • DraxEngland and Wales, Storage with solar or windRenamed from Drax - New Connection
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO