Lakeside Energy Drax
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted 6 May 2021
North Yorkshire, reference 2020/1357/FULM · Source: REPD - Technology
- Storage
- Total capacity
- 99.9 MW
- Connected now
- 99.9 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001522
- In the register since
- July 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 register0.9 MW now connected
- 30 May 2025 registerCapacity changed from 99 MW to 99.9 MW
- 31 Jan 2025 register99 MW now connected
- 31 Jan 2025 registerCapacity changed from 99.9 MW to 99 MW
- 24 Dec 2024 registerConnection date moved from 29 Mar 2024 to 29 Sep 2024 (+6 months)
- 24 Dec 2024 registerStatus changed from Consents Approved to Built
- 30 Jul 2024 registerSubstation name updated in the register (from Drax GSP to Drax 132kV Substation)
- 30 May 2023 registerConnection date moved from 31 Oct 2023 to 29 Mar 2024 (+5 months)
- 30 Mar 2022 registerConnection point changed from Drax to Drax GSP
- 31 Dec 2021 registerCustomer changed from RENEWABLE ENERGY SYSTEMS LIMITED to Lakeside Energy Storage Limited
- 30 Jul 2021 registerAdded to the register
Also at Drax 132kV Substation
Substation view1 other project, 190 MW still to connect at this substation in total.