- Connection date
- 30 Oct 2029
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage + Solar
- Total capacity
- 190 MW
- Connected now
- 0 MW
- Still to connect
- 190 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001355
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Awaiting Consents
- 27 Aug 2024 registerConnection point changed from Drax 400kV Substation to Drax 132kV Substation
- 27 Aug 2024 registerConnection date moved from 30 Jun 2025 to 30 Oct 2029 (+52 months)
- 27 Aug 2024 registerTechnology changed from Storage to Storage, Solar
- 30 Jun 2023 registerRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (190 MW from 30 Jun 2025)
- 30 Mar 2022 registerConnection point changed from Drax to Drax 400kV Substation
- 30 Apr 2021 registerRenamed from Drax - New Connection
Also at Drax 132kV Substation
Substation view1 other project, 190 MW still to connect at this substation in total.