Drakelow 132kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Oaklands Farm Solar PV | OAKLANDS FARM SOLAR LIMITED. | Storage with solar or wind | 162 | 30 Jun 2027 | Gate 2 | Consents Approved |
| Drakelow | ENSO GREEN HOLDINGS V LIMITED | Storage | 120 | 1 Dec 2027 | Gate 1 | Scoping |
| Royle Farm BESS | ALUDRA BESS LTD | Storage | 90 | 31 Oct 2028 +12 mo | Gate 2 | Consents Approved |
Recent changes
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- Royle Farm BESSEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Royle Farm BESSEngland and Wales, StorageConnection date moved from 31 Oct 2027 to 31 Oct 2028 (+12 months)+12 mo
- Royle Farm BESSEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- DrakelowEngland and Wales, StorageMarked as Gate 1
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windConnection date moved from 1 Jun 2025 to 30 Jun 2027 (+25 months)+25 mo
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windCustomer changed from BAYWA R.E. UK LIMITED to OAKLANDS FARM SOLAR LIMITED.
- Royle Farm BESSEngland and Wales, StorageAdded to the registerNew
- DrakelowEngland and Wales, StorageCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO GREEN HOLDINGS V LIMITED
- DrakelowEngland and Wales, StorageCustomer changed from ENSO Green Holdings V Limited to ENSO GREEN HOLDINGS LIMITED
- DrakelowEngland and Wales, StorageConnection point changed from Drakelow 400kV Substation to Drakelow 132kV Substation
- DrakelowEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- DrakelowEngland and Wales, StorageCapacity changed from 57 MW to 120 MW
- DrakelowEngland and Wales, StorageConnection date moved from 31 Oct 2024 to 1 Dec 2027 (+37 months)+37 mo
- DrakelowEngland and Wales, StorageCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO Green Holdings V Limited
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windSubstation name updated in the register (from Drakelow 132kV to Drakelow 132kV Substation)
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
- DrakelowEngland and Wales, StorageSubstation name updated in the register (from Drakelow 400kV to Drakelow 400kV Substation)
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windCapacity changed from 79.6 MW to 162 MW
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windConnection date moved from 1 Oct 2023 to 1 Jun 2025 (+20 months)+20 mo
- Oaklands Farm Solar PVEngland and Wales, Storage with solar or windConnection date moved from 10 Jan 2023 to 1 Oct 2023 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?