Oaklands Farm Solar PV
- Connection date
- 30 Jun 2027
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 19 Jun 2025
The Planning Inspectorate - National Infrastructure, reference EN010122 · Source: REPD - Technology
- Storage + Solar
- Total capacity
- 162 MW
- Connected now
- 0 MW
- Still to connect
- 162 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001004
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerStatus changed from Scoping to Consents Approved
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 21 Nov 2025 registerConnection date moved from 1 Jun 2025 to 30 Jun 2027 (+25 months)
- 29 Aug 2025 registerCustomer changed from BAYWA R.E. UK LIMITED to OAKLANDS FARM SOLAR LIMITED.
- 30 Jan 2024 registerSubstation name updated in the register (from Drakelow 132kV to Drakelow 132kV Substation)
- 30 Jan 2024 registerTechnology changed from Solar to Storage, Solar
- 25 Feb 2022 registerCapacity changed from 79.6 MW to 162 MW
- 25 Feb 2022 registerConnection date moved from 1 Oct 2023 to 1 Jun 2025 (+20 months)
- 26 Feb 2021 registerConnection date moved from 10 Jan 2023 to 1 Oct 2023 (+9 months)
Also at Drakelow 132kV Substation
Substation view2 other projects, 372 MW still to connect at this substation in total.