Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

OAKLANDS FARM SOLAR LIMITED.

Customer named in the TEC register

1project in the register
162 MWstill to connect
162 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Oaklands Farm Solar PVDrakelow 132kV SubstationStorage with solar or wind16230 Jun 2027Gate 2Consents Approved

Recent changes

  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windConnection date moved from 1 Jun 2025 to 30 Jun 2027 (+25 months)+25 mo
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windCustomer changed from BAYWA R.E. UK LIMITED to OAKLANDS FARM SOLAR LIMITED.
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windSubstation name updated in the register (from Drakelow 132kV to Drakelow 132kV Substation)
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windCapacity changed from 79.6 MW to 162 MW
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windConnection date moved from 1 Oct 2023 to 1 Jun 2025 (+20 months)+20 mo
  • Oaklands Farm Solar PVEngland and Wales, Storage with solar or windConnection date moved from 10 Jan 2023 to 1 Oct 2023 (+9 months)+9 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO