Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Coupar Angus 132/33kV GSP

North Scotland, SSEN Transmission

5projects in the register
156 MWstill to connect
66 MWof that with Gate 2 offers
17.5 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Coupar Angus BatteryCOUPAR LIMITEDStorage4021 Feb 2022 Past dateNot statedConsents Approved
Keithick 16 Solar & BESSSIRIUS ECODEV (KEITHICK) LTDStorage with solar or wind1631 Dec 2026 +6 moGate 2Consents Approved
Keithick EstateSIRIUS ECODEV (STIRLING) LTDStorage with solar or wind5031 Dec 2026 +6 moGate 2Under Construction/Commissioning
Coupar Solar FarmCOUPAR TWO LIMITEDSolar49.930 Apr 2027Not statedScoping
Tullymurdoch Wind FarmTULLYMURDOCH LIMITEDOnshore wind0ConnectedNot statedBuilt

Recent changes

  • Keithick 16 Solar & BESSNorth Scotland, Storage with solar or windConnection date moved from 30 Jun 2026 to 31 Dec 2026 (+6 months)+6 mo
  • Keithick 16 Solar & BESSNorth Scotland, Storage with solar or windGiven a Gate 2 connection offerGate 2
  • Keithick EstateNorth Scotland, Storage with solar or windStatus changed from Consents Approved to Under Construction/Commissioning
  • Keithick EstateNorth Scotland, Storage with solar or windConnection date moved from 30 Jun 2026 to 31 Dec 2026 (+6 months)+6 mo
  • Keithick EstateNorth Scotland, Storage with solar or windGiven a Gate 2 connection offerGate 2
  • Coupar Angus BatteryNorth Scotland, StorageSubstation name updated in the register (from Coupar Angus GSP to Coupar Angus 132/33kV GSP)
  • Coupar Solar FarmNorth Scotland, SolarSubstation name updated in the register (from Coupar Angus GSP to Coupar Angus 132/33kV GSP)
  • Keithick 16 Solar & BESSNorth Scotland, Storage with solar or windSubstation name updated in the register (from Coupar Angus GSP to Coupar Angus 132/33kV GSP)
  • Keithick EstateNorth Scotland, Storage with solar or windSubstation name updated in the register (from Coupar Angus GSP to Coupar Angus 132/33kV GSP)
  • Tullymurdoch Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Coupar Angus GSP to Coupar Angus 132/33kV GSP)
  • Keithick 16 Solar & BESSNorth Scotland, Storage with solar or windConnection date moved from 30 Jun 2024 to 30 Jun 2026 (+24 months)+24 mo
  • Keithick EstateNorth Scotland, Storage with solar or windConnection date moved from 30 Jun 2024 to 30 Jun 2026 (+24 months)+24 mo
  • Coupar Solar FarmNorth Scotland, SolarConnection date moved from 31 Oct 2025 to 30 Apr 2027 (+18 months)+18 mo
  • Coupar Solar FarmNorth Scotland, SolarAdded to the registerNew
  • Keithick 16 Solar & BESSNorth Scotland, Storage with solar or windStatus changed from Scoping to Consents Approved
  • Keithick EstateNorth Scotland, Storage with solar or windStatus changed from Awaiting Consents to Consents Approved
  • Keithick EstateNorth Scotland, Storage with solar or windCustomer changed from Sirius Ecodev (Keithick) Limited to SIRIUS ECODEV (STIRLING) LTD
  • Keithick 16 Solar & BESSNorth Scotland, Storage with solar or windAdded to the registerNew
  • Keithick EstateNorth Scotland, Storage with solar or windConnection date moved from 30 Apr 2026 to 30 Jun 2024 (−22 months)−22 mo
  • Coupar Angus BatteryNorth Scotland, StorageSubstation name updated in the register (from Coupar Angus to Coupar Angus GSP)
  • Keithick EstateNorth Scotland, Storage with solar or windSubstation name updated in the register (from Coupar Angus to Coupar Angus GSP)
  • Tullymurdoch Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Coupar Angus to Coupar Angus GSP)
  • Keithick EstateNorth Scotland, Storage with solar or windAdded to the registerNew
  • Coupar Angus BatteryNorth Scotland, StorageConnection date moved from 1 Sep 2021 to 21 Feb 2022 (+6 months)+6 mo
  • Coupar Angus BatteryNorth Scotland, StorageRenamed from Coupar Angus Battery Storage
  • Coupar Angus BatteryNorth Scotland, StorageConnection date moved from 9 Jan 2021 to 1 Sep 2021 (+8 months)+8 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO