Keithick 16 Solar & BESS
- Connection date
- 31 Dec 2026 +6 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 16 MW
- Connected now
- 0 MW
- Still to connect
- 16 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-001890
- In the register since
- March 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Sep 2026 registerConnection date moved from 30 Jun 2026 to 31 Dec 2026 (+6 months)
- 21 Sep 2026 registerGiven a Gate 2 connection offer
- 2 Jan 2026 registerSubstation name updated in the register (from Coupar Angus GSP to Coupar Angus 132/33kV GSP)
- 30 May 2025 registerConnection date moved from 30 Jun 2024 to 30 Jun 2026 (+24 months)
- 30 Jun 2023 registerStatus changed from Scoping to Consents Approved
- 31 Mar 2023 registerAdded to the register
Also at Coupar Angus 132/33kV GSP
Substation view4 other projects, 156 MW still to connect at this substation in total. 40 MW is due to connect here before this project’s connection date of 31 Dec 2026.
- Coupar Angus BatteryCOUPAR LIMITED, Storage, Not statedFeb 202240 MW
- Keithick EstateSIRIUS ECODEV (STIRLING) LTD, Storage with solar or wind, Gate 2Dec 202650 MW
- Coupar Solar FarmCOUPAR TWO LIMITED, Solar, Not statedApr 202749.9 MW
- Tullymurdoch Wind FarmTULLYMURDOCH LIMITED, Onshore wind, Not statedConnected17.5 MW