Connah's Quay 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Deeside Power Station | DEESIDE POWER (UK) LIMITED | Storage | 189 | 25 Oct 2026 Past date | Gate 2 | Built |
| Port of Mostyn | MOSTYN SEAPOWER LIMITED | Hydro & marine | 210 | 1 Dec 2030 | Gate 1 | Scoping |
| Icewind Connah's Quay | KARI ENERGY LIMITED | Offshore wind | 1,000 | 1 Nov 2033 | Gate 1 | Scoping |
| Connah's Quay | Uniper UK Limited | Thermal (gas, biomass, waste) | 0 | Connected | Not stated | Built |
Recent changes
- Deeside Power StationEngland and Wales, StorageStatus changed from Consents Approved to Built
- Deeside Power StationEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
- Port of MostynEngland and Wales, Hydro & marineStage 1: Marked as Gate 1
- Port of MostynEngland and Wales, Hydro & marineStage 2: Marked as Gate 1
- Port of MostynEngland and Wales, Hydro & marineStage 3: Marked as Gate 1
- Deeside Power StationEngland and Wales, StorageConnection point changed from Deeside 400kV Substation to Connah's Quay 400kV Substation
- Connah's QuayEngland and Wales, Thermal (gas, biomass, waste)Customer changed from C.GEN Killingholme Limited to Uniper UK Limited
- Icewind Connah's QuayEngland and Wales, Offshore windMarked as Gate 1
- Connah's QuayEngland and Wales, Thermal (gas, biomass, waste)Customer changed from Uniper UK Limited to C.GEN Killingholme Limited
- Deeside Power StationEngland and Wales, StorageConnection point changed from Connah's Quay 400kV Substation to Deeside 400kV Substation
- Deeside Power StationEngland and Wales, StorageTechnology changed from Storage, Gas engines to Storage, Reactive compensation
- Port of MostynEngland and Wales, Hydro & marineStage 2: Capacity changed from 140 MW to 70 MW
- Port of MostynEngland and Wales, Hydro & marineStage 3: Capacity changed from 210 MW to 70 MW
- Deeside Power StationEngland and Wales, Storage1 MW now connectedConnected
- Deeside Power StationEngland and Wales, StorageStatus changed from Scoping to Consents Approved
- Port of MostynEngland and Wales, Hydro & marineRestructured from 1 stage (210 MW from 1 Apr 2027) to 3 stages (70 MW from 1 Dec 2030, 140 MW from 1 Jun 2031, 210 MW from 1 Jan 2032). First connection date +44 months+44 mo
- Deeside Power StationEngland and Wales, Storage1 MW no longer connected
- Deeside Power StationEngland and Wales, StorageConnection point changed from Deeside 400kV Substation to Connah's Quay 400kV Substation
- Deeside Power StationEngland and Wales, StorageCapacity changed from 189 MW to 190 MW
- Deeside Power StationEngland and Wales, StorageStatus changed from Built to Scoping
- Deeside Power StationEngland and Wales, StorageTechnology changed from Storage, Reactive compensation to Storage, Gas engines
- Icewind Connah's QuayEngland and Wales, Offshore windCustomer changed from Hecate Offshore Wind Limited to KARI ENERGY LIMITED
- Deeside Power StationEngland and Wales, StorageConnection date moved from 31 Oct 2033 to 25 Oct 2026 (−84 months)−84 mo
- Icewind Connah's QuayEngland and Wales, Offshore windSubstation name updated in the register (from Connah's Quay GSP to Connah's Quay 400kV Substation)
- Deeside Power StationEngland and Wales, StorageTechnology changed from Reactive compensation to Storage, Reactive compensation
- Icewind Connah's QuayEngland and Wales, Offshore windCustomer changed from HECATE INDEPENDENT POWER LIMITED to Hecate Offshore Wind Limited
- Deeside Power StationEngland and Wales, StorageCapacity changed from 0 MW to 189 MW
- Deeside Power StationEngland and Wales, StorageConnection date set to 31 Oct 2033
- Connah's QuayEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Connah's Quay 400kV to Connah's Quay 400kV Substation)
- Icewind Connah's QuayEngland and Wales, Offshore windSubstation name updated in the register (from Connah's Quay to Connah's Quay GSP)
- Port of MostynEngland and Wales, Hydro & marineSubstation name updated in the register (from Connah's Quay 400kV to Connah's Quay 400kV Substation)
- Port of MostynEngland and Wales, Hydro & marineConnection date moved from 1 Apr 2025 to 1 Apr 2027 (+24 months)+24 mo
- Deeside Power StationEngland and Wales, StorageTechnology changed from Gas (CCGT) to Reactive compensation
- Icewind Connah's QuayEngland and Wales, Offshore windCustomer changed from HECTATE INDEPENDENT POWER LIMITED to HECATE INDEPENDENT POWER LIMITED
- Icewind Connah's QuayEngland and Wales, Offshore windAdded to the registerNew
- Port of MostynEngland and Wales, Hydro & marineConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)+12 mo
- Port of MostynEngland and Wales, Hydro & marineConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose