Port of Mostyn
- Connection date
- 1 Dec 2030
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Tidal
- Total capacity
- 210 MW
- Connected now
- 0 MW
- Still to connect
- 210 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000421
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 70 | 70 | 1 Dec 2030 | Gate 1 | Scoping |
| 2 | 0 | 70 | 140 | 1 Jun 2031 | Gate 1 | Scoping |
| 3 | 0 | 70 | 210 | 1 Jan 2032 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Jun 2026 registerStage 1: Marked as Gate 1
- 16 Jun 2026 registerStage 2: Marked as Gate 1
- 16 Jun 2026 registerStage 3: Marked as Gate 1
- 27 Jun 2025 registerStage 2: Capacity changed from 140 MW to 70 MW
- 27 Jun 2025 registerStage 3: Capacity changed from 210 MW to 70 MW
- 28 Feb 2025 registerRestructured from 1 stage (210 MW from 1 Apr 2027) to 3 stages (70 MW from 1 Dec 2030, 140 MW from 1 Jun 2031, 210 MW from 1 Jan 2032). First connection date +44 months
- 23 Dec 2022 registerSubstation name updated in the register (from Connah's Quay 400kV to Connah's Quay 400kV Substation)
- 31 May 2022 registerConnection date moved from 1 Apr 2025 to 1 Apr 2027 (+24 months)
- 30 Apr 2021 registerConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)
Also at Connah's Quay 400kV Substation
Substation view3 other projects, 1.4 GW still to connect at this substation in total. 189 MW is due to connect here before this project’s connection date of 1 Dec 2030.