Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Carrington 400KV Substation

England and Wales, National Grid Electricity Transmission

3projects in the register
2.1 GWstill to connect
680 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Cryogenic Battery System (Synchronous)CRYOBATTERY ONE LIMITEDStorage49.98 Nov 2026Not statedUnder Construction/Commissioning
CarringtonCARRINGTON STORAGE LIMITEDStorage68031 Oct 2027 +12 moGate 2Consents Approved
Trafford 2 BESSFUTURE POINT MANCHESTER LIMITEDStorage1,40030 Oct 2038Not statedScoping

Left the register since January 2021: CPG Power (49.9 MW).

Recent changes

  • CarringtonEngland and Wales, StorageGiven a Gate 2 connection offerGate 2
  • CarringtonEngland and Wales, StorageConnection date moved from 30 Oct 2026 to 31 Oct 2027 (+12 months)+12 mo
  • CarringtonEngland and Wales, StorageTechnology changed from Gas (CCGT) to Storage
  • Trafford 2 BESSEngland and Wales, StorageCustomer changed from CARLTON POWER DEVELOPMENTS NO. 8 LIMITED to FUTURE POINT MANCHESTER LIMITED
  • CarringtonEngland and Wales, StorageRestructured from 2 stages (1,040 MW from 30 Oct 2025, 1,040 MW from 30 Oct 2036) to 1 stage (680 MW from 30 Oct 2026). First connection date +12 months+12 mo
  • Cryogenic Battery System (Synchronous)England and Wales, StorageStage 1: Status changed from Consents Approved to Under Construction/Commissioning
  • Cryogenic Battery System (Synchronous)England and Wales, StorageStage 2: Status changed from Consents Approved to Under Construction/Commissioning
  • Cryogenic Battery System (Synchronous)England and Wales, StorageRestructured from 1 stage (49.9 MW from 31 Oct 2024) to 2 stages (0 MW from 8 May 2026, 49.9 MW from 8 Nov 2026). First connection date +24 months+24 mo
  • Trafford 2 BESSEngland and Wales, StorageAdded to the registerNew
  • CarringtonEngland and Wales, StorageRenamed from Trafford Power
  • CarringtonEngland and Wales, StorageCustomer changed from WAINSTONES ENERGY LIMITED to Carrington Storage Limited
  • CPG PowerEngland and Wales, Thermal (gas, biomass, waste)Left the register (49.9 MW from 30 Jun 2026)49.9 MW
  • CarringtonEngland and Wales, StorageRestructured from 1 stage (2,050 MW from 15 Jul 2020) to 2 stages (1,040 MW from 30 Oct 2025, 1,040 MW from 30 Oct 2036). First connection date +63 months+63 mo
  • Cryogenic Battery System (Synchronous)England and Wales, StorageTechnology changed from Storage to Storage, Reactive compensation
  • CarringtonEngland and Wales, StorageSubstation name updated in the register (from Carrington 400kV to Carrington 400KV Substation)
  • CPG PowerEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Carrington 400kV to Carrington 400KV Substation)
  • Cryogenic Battery System (Synchronous)England and Wales, StorageConnection date moved from 26 Aug 2023 to 31 Oct 2024 (+14 months)+14 mo
  • Cryogenic Battery System (Synchronous)England and Wales, StorageStatus changed from Awaiting Consents to Consents Approved
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO